Capital Program
Growth/Major project capital expenditures decreased slightly in 2005. Spending on the
Stage 3 expansion, which will increase the output capacity of Syncrude’s upgrading
facilities at Mildred Lake by almost 50 per cent, represented the majority of major project
capital expenditures in 2005.
Other major projects in 2005 included the South West Quadrant Mine Replacement
project. This project, now completed, replaces bitumen production from the base mine
at Mildred Lake and provides additional feed for Syncrude’s expanded upgrader through
new mining trains in the Mildred Lake North and Aurora mines. The new North Mine
Auxiliary Production System was commissioned in May 2005, and a third mining train
at Aurora finished construction and began start-up in December 2005.
Development engineering work continued on the Syncrude Emissions Reduction
project, which reached 14 per cent completion of engineering design at year-end.
This project will reduce total emissions of sulphur dioxide by 60 per cent and particulate
emissions by 50 per cent from current levels, and is targeted for completion and
start-up in 2009.
More about this project...
|